Friday 24 October 2014

Winter project work

Following on from the members' open forum (where the greens committee presented the golf course masterplan and winter projects), I thought it a good idea to reiterate exactly what we shall be doing.

Starting Monday 17 November, Lakeland Earthworks will be on site for approximately 2 weeks to carry out a number of small projects.

This will include the following:

- Reshape greens surround at 2nd
- Reshape left green side bunker at 2nd 
- Rebuild 3rd white tee
- Create tee bank to right of 12th tee
- Remove small mound to left of 3rd approach
- Create new forward tee at 4th
- Reshape greens surround at 4th
- Create new bunker left of 4th green
- Remove mound behind 7th green
- Reshape greens surround behind 7th
- Create new forward tee at 8th

These are all coded on the golf course masterplan. Although they are not of utmost priority, they fit into the budget nicely and given a contractor had to build 2 new forward tees for the golf club at holes 4 & 8, it was considered a good idea to complete these small projects at the same time.

For your reference when looking at the golf course masterplan, they are as follows:

- 2-11P
- 2-11Q
- 2-11R
- 2-11S
- 3-12A
- 3-12B
- 3-12C
- 3-12F
- 4-13G
- 4-13H
- 4-13I
- 4-13S
- 4-13T
- 4-13V
- 8-17B

Hope this all makes sense!

Have a great weekend and enjoy your golf!